Panama 2-2-3 Work Schedule — the Rotation, the Hours and the Coverage Proof

Four crews, twelve-hour shifts, 2 on and 2 off and 3 on — then the same again on nights. This is the whole Panama rotation, with the coverage checked day by day.

4 crews168 h per 28 daysFortnight flip

The shift calendar

First ten days — Crew A, Panama 2-2-3

  1. Mon 4DAY12 h
  2. Tue 5DAY12 h
  3. Wed 6OFF—
  4. Thu 7OFF—
  5. Fri 8DAY12 h
  6. Sat 9DAY12 h
  7. Sun 10DAY12 h
  8. Mon 11OFF—
  9. Tue 12OFF—
  10. Wed 13DAY12 h

Crew A · Panama 2-2-3 · overtime after 40 h

FLSA default: overtime after 40 h in each 7-day workweek; over 28 days that is 160 h.

  • 42.0average hours a week168 h per 28-day cycle
  • 2,184hours a year1,976 regular + 208 overtime
  • 4.0overtime h a week26 of 52 weeks carry overtime
  • $91,520gross a year$40/h · OT ×1.5
  • 25full weekends off624 weekend hours a year
  • 3longest break, days12 h shortest rest · 0 night→day
Hours by workweek (Sunday–Saturday), first 8 weeks
Week ofHoursRegularOvertime
2027-01-0348.040.08.0
2027-01-1036.036.0—
2027-01-1748.040.08.0
2027-01-2436.036.0—
2027-01-3148.040.08.0
2027-02-0736.036.0—
2027-02-1448.040.08.0
2027-02-2136.036.0—

Crew A · Panama 2-2-3 · 42.0 h a week · 208 h overtime a year at 40 h · 3-day longest break

January 2027
SunMonTueWedThuFriSat
1OFF2OFF
3OFF4DAY5DAY6OFF7OFF8DAY9DAY
10DAY11OFF12OFF13DAY14DAY15OFF16OFF
17OFF18NIGHT19NIGHT20OFF21OFF22NIGHT23NIGHT
24NIGHT25OFF26OFF27NIGHT28NIGHT29OFF30OFF
31OFF
  • DAY Day 07:00–19:00
  • NIGHT Night 19:00–07:00
  • OFF Off
Compare with another rotation

Both columns use the same 52 workweeks, the same 40-hour threshold, and the same $40/h at OT ×1.5.

Panama 2-2-3 versus DuPont
MeasurePanama 2-2-3DuPont
Cycle length28 days28 days
Hours per cycle168 h168 h
Average week42.0 h42.0 h
Overtime a year208 h468 h
Full weekends off2525
Longest break3 days7 days
Shortest rest12 h12 h
Night → day turns00
Weekend hours a year624 h624 h
Gross at this rate$91,520$96,720

The cycle, block by block

Checked day by day across all 28 days of the cycle: exactly 1 crew on days, 1 on nights, and 2 off.

Crew A — 28-day cycle, 12-hour shifts
BlockDaysLengthShiftHours so far
2D1–22Day 07:00–19:0024 h
2O3–42Off24 h
3D5–73Day 07:00–19:0060 h
2O8–92Off60 h
2D10–112Day 07:00–19:0084 h
3O12–143Off84 h
2N15–162Night 19:00–07:00108 h
2O17–182Off108 h
3N19–213Night 19:00–07:00144 h
2O22–232Off144 h
2N24–252Night 19:00–07:00168 h
3O26–283Off168 h
28-day cycle1–28282D-2O-3D-2O-2D-3O-2N-2O-3N-2O-2N-3O168 h
All crews — shifts, hours and the average week
CrewBlock shorthandShiftsHours / cycleAvg h / week
Crew A2D-2O-3D-2O-2D-3O-2N-2O-3N-2O-2N-3O14168 h42.0 h
Crew B2O-2D-3O-2D-2O-3D-2O-2N-3O-2N-2O-3N14168 h42.0 h
Crew C2N-2O-3N-2O-2N-3O-2D-2O-3D-2O-2D-3O14168 h42.0 h
Crew D2O-2N-3O-2N-2O-3N-2O-2D-3O-2D-2O-3D14168 h42.0 h

Shorthand reads as count then code: 4N is four nights, 3O three off, 7O a seven-day break. Hours are counted from the first block of the cycle. The pattern repeats, so a month that begins before the chosen start date shows where that earlier phase would have placed the crew.

What makes a schedule a Panama schedule

A Panama schedule is a four-crew, twelve-hour rotation built on a fourteen-day block: two days on, two off, three on, two off, two on, three off. Two crews work every calendar day — one on days, one on nights — and two are off. That is the whole definition, and everything else about Panama follows from it.

The pattern is old enough to have several names. Continuous-operations plants call it 2-2-3, hospitals sometimes call it a Pitman schedule, and recruiters describe the same fourteen days as 2-3-2 when they are counting working blocks instead of alternations. If you are comparing offers, compare the sequence, not the label.

The fortnight flip, and why crews change sides

After fourteen days the crews that were on days move to nights and the crews that were on nights move to days. That flip is what makes the full cycle twenty-eight days rather than fourteen, and it is also what makes Panama fair: over a month every crew carries the same number of day shifts and night shifts, so nobody is permanently nocturnal.

Not every site flips on the same interval. Flipping every fortnight is the most common form and the one this page defaults to. Some operations flip every four weeks instead, which halves the number of body-clock changes per year at the cost of a longer stretch on nights; the picker includes that as a 56-day cycle so the two can be compared on identical hours. A few sites never flip at all, keeping two crews permanently on days and two permanently on nights — that is the fixed-shift 14-day variant in the same list.

The coverage proof

The claim that makes Panama work is that two crews are always working, one per shift, with no gaps and no doubles. That claim is checkable, so the page checks it: for every one of the twenty-eight days in the cycle it counts how many crews are on days, how many on nights, and how many are off, and prints the result under the calendar.

The result is twenty-eight days of exactly one day crew, one night crew and two crews off. If you switch to the four-week-flip variant the same check runs over fifty-six days and still holds. This is the kind of thing a hand-drawn rota gets wrong once a quarter, usually on the day the clocks change or the week a holiday falls.

Hours, weekends and the overtime line

Each crew works fourteen twelve-hour shifts per twenty-eight days: 168 hours, which is 42 hours a week on average, or 2,184 hours a year. Every crew gets a three-day break every other week, and a full Saturday-and-Sunday weekend off roughly every second week — 25 of them at the default anchor — more than a five-day office week gets, though not consecutive.

The overtime story is where Panama surprises people. Because the fourteen-day block does not divide evenly into seven-day workweeks, the weeks are not all 42 hours: they alternate. Measured Sunday to Saturday at a Monday-anchored cycle the weeks come out at 48 and 36 hours, so exactly one week in two carries eight overtime hours. Slice the same shifts Monday to Sunday and the boundary cuts differently — the tool lets you move it, because your employer already has.

At a forty-hour threshold the year works out at 2,184 hours with 208 of them overtime. Under the § 207(k) fire-protection threshold of 53 hours the overtime drops sharply, because a 48-hour week no longer crosses the line at all. Same shifts, same employer, two very different payrolls — which is why private ambulance and fire-based EMS argue about this classification so much.

Who Panama suits, and what it costs

Panama is popular wherever the job needs twenty-four-hour cover with twelve-hour shifts: control rooms, refineries, hospitals, campus security. It gives a predictable fortnight, a three-day weekend every other week, and equal shares of days and nights across a month.

The cost is the flip. Two full weeks on nights is long enough to adapt to and short enough that you have to adapt back, so the changeover week is usually the one people describe as lost. The four-week-flip variant exists precisely because some crews find that fortnightly switching is worse than a longer block. Neither answer is universal — draw both and look at your own calendar before you commit.

Questions this page gets asked

How many hours does a Panama 2-2-3 schedule work?

168 hours per 28-day cycle, which is 42 a week on average and about 2,184 hours a year at twelve-hour shifts. Fourteen shifts of twelve hours per crew per cycle, with two crews working each day and two off.

Why is it called a Panama schedule?

The name is usually traced to its use on large continuous-operation projects in the Panama Canal zone, where round-the-clock work with four crews and twelve-hour shifts needed a fair rotation. The arithmetic does not depend on the origin: 2 on, 2 off, 3 on, 2 off, 2 on, 3 off over fourteen days.

Does Panama give every crew the same number of nights?

Yes, when the cycle includes the day/night flip. Over the full 28-day cycle each crew works seven day shifts and seven night shifts, which is why the flip exists. In the fixed-shift 14-day variant two crews are permanently on days and two permanently on nights, and the tool labels that variant separately rather than pretending it is the same job.

How many weekends off do you get on 2-2-3?

A full weekend every other week, which is 25 in a 52-workweek year at the default anchor and 26 when the cycle lines up the other way. A full weekend means both Saturday and Sunday without a shift, and the card counts them from the actual calendar rather than from the pattern name.

Is the 2-2-3 pattern legal for overtime?

The pattern is not what the law regulates; the hours in each workweek are. Under the FLSA default, hours over 40 in a workweek are overtime, and a 2-2-3 crew will exceed 40 in roughly half its weeks. Fire-protection and law-enforcement employees of public agencies may instead be paid under the § 207(k) work-period standard, which this page offers as a toggle with the 212-hour, 28-day figure shown alongside it.